Ukrenergo has resumed the operation of a 330 kV high-voltage overhead line, which is part of the backup power supply scheme for ZNPP. This is reported by NNEGC Energoatom, UNN reports.
Details
Today, on April 6, at 18:09, Ukrainian power engineers restored the operation of the second 330 kV power line Zaporizhzhia TPP-Ferrosplavna, which was disconnected after enemy shelling.
The Zaporizhzhya TPP-Ferrosplavna line together with the 750 kV Zaporizhzhya NPP-Dniprovska line ensures stable power supply to the power plant.
Recall
Since the beginning of the russian occupation, Zaporizhzhia NPP has faced 8 full power outages and one partial one.
Zaporizhzhya NPP is on the verge of another blackout, power line disconnected due to Russian shelling - EnergoatomApril 4 2024, 07:45 AM • 24919 views