$45.05↓0.15€49.53↓0.04
10:19 AM • 764 views
Poland reported that two Russian missiles and a drone had fallen on its territory
10:00 AM • 3070 views
The EU opens the way for Ukraine to the final negotiating clusters — Hungary approves
08:08 AM • 16366 views
Axios revealed the details of the talks in Berlin, including Trump's call after the summit with Xi and Putin
Exclusive
07:05 AM • 18170 views
The failure of the NABU and SAPO heads to appear at the Temporary Special Commission meeting will look like an attempt to avoid answering questions or conceal certain circumstances, a lawyer says.
05:16 AM • 31560 views
About 50 missiles simultaneously over Ukraine – Russia attacks the western regions; there are fatalities in Kyiv
04:57 AM • 31749 views
Some trolleybuses were suspended and bus routes changed in Kyiv – the aftermath of the nighttime attack is paralyzing transport
04:34 AM • 28118 views
The Russians damaged three bridges in Kyiv at once — traffic between the capital’s banks was restricted after missile strikes
November 20, 04:15 AM • 24672 views
After the destruction of the Crimean Bridge, the "Novorossiya" highway became even deadlier for the occupiers — ATESH
November 20, 03:16 AM • 27989 views
Russia was offered an energy truce for the entire winter – the "coalition of the willing" put forward a demand to the Kremlin
November 20, 02:15 AM • 31056 views
Russia may have secretly tested the "Sarmat" nuclear missile — satellite images reveal suspicious activityPhoto

Information agency «Ukrainian National News»

Subject in the field of online media; media identifier - R40-05926

This resource is intended for persons who have reached the age of 21.

All rights reserved. © 2007 — 2026

Погода
+8°
1m/s
97%
732mm
Advertisement

Construction of the metro to Vynohradar: KCSA told about the progress of work

Kyiv • UNN

 • 23356 views

In Kyiv, work is underway around the clock at the construction sites for the metro to Vynohradar. The construction of the dismantling shaft, waterproofing and soil development works continue.

Construction of the metro to Vynohradar: KCSA told about the progress of work

In the capital, the construction of the metro to Vynohradar is underway at several sites simultaneously. Work is underway on the construction of a dismantling shaft, waterproofing and soil development. This was reported by KCSA, according to UNN. 

Details

According to KCSA, construction at the sites is ongoing around the clock.

Construction of a dismantling shaft continues at the site, near the Syrets metro station, which will be used to remove the tunnel boring shield in the future.

In another area, where two-level tunnels have already been partially constructed, waterproofing, reinforcement and concrete walls are being installed.

It is also reported that soil development is underway, as well as the installation of firing belts for the further construction of two-level tunnels.

Ground development works are underway at another site. Drilling rigs are also being set up there to create a stable foundation for further construction.

Recall 

"Kyiv Metro has signed a contract with Avtostrada Group to continue construction of the Syretsko-Pecherska subway line to Vynohradar. The cost of the work is UAH 13.785 billion, and the construction period is 30 months.

The metro to Vynohradar is planned to be completed in 2.5 years.