Today, November 8, external power supply was restored at the temporarily occupied Zaporizhzhia Nuclear Power Plant (ZNPP) via the "Ferosplavna-1" power line following another blackout at the plant. This was reported by Energoatom, according to UNN.
The Zaporizhzhia NPP is once again receiving external power from Ukraine's power system. At 17:41, the 330 kV "Ferosplavna-1" power line was switched on
At the same time, the situation at the ZNPP remains extremely dangerous. As long as the plant remains under occupation, the threat of power outages—as well as the threat to nuclear and radiation safety—persists.