In Britain, the route of an energy project was changed because of the "grave" of Dobby the elf from "Harry Potter"

Kyiv • UNN

 • 1522 views

Developers of the £430 million Greenlink power cable revised its route following complaints from "Harry Potter" fans. The cable was supposed to come ashore at a beach in Wales where Dobby the elf's death was filmed.

In Britain, the route of an energy project was changed because of the "grave" of Dobby the elf from "Harry Potter"

The developers of the Greenlink subsea power cable revised the route following complaints from Harry Potter fans, who opposed laying the cable near an unofficial memorial to one of the series' characters, the elf Dobby. The Telegraph reports this, citing former project director Simon Ludlam, according to UNN.

Details

It is noted that the energy project cost approximately £430 million. The project involves the Greenlink subsea cable, which is intended to transmit electricity between the United Kingdom and Ireland.

The uproar over the elf's fictional grave is just one example of the difficulties facing a major British infrastructure project. In 2024, the head of HS2 said that an additional £100 million would have to be spent on a 1-kilometre tunnel to protect rare bats, as the high-speed railway line would pass through an ancient woodland in Buckinghamshire

- the publication writes.

It is indicated that the cable was planned to come ashore at Freshwater West beach in Pembrokeshire, Wales. This is where Dobby's death scene in the film "Harry Potter and the Deathly Hallows" was filmed.

After the film was released, the beach became popular with franchise fans. Fans created an unofficial memorial to the character there and leave painted stones, messages and socks at the site — the item thanks to which "Dobby became free".