Construction of 1 GW of gas generation capacity will be implemented with a delay - Advisor to the Prime Minister

 • 19210 переглядiв

The construction of 1 GW of gas-fired power generation capacity in Ukraine is postponed due to delays in equipment and project preparation. An advisor to the Prime Minister confirmed the postponement of the implementation to next year.

The construction of up to 1 GW of gas generation capacity, which was planned for this year, will be implemented with a conditional delay due to the preparation of projects and lack of equipment. This was stated by the Prime Minister's Advisor on Energy Natalia Boyko during the Kyiv International Economic Forum, UNN reports.

Many projects have been moved to the next year's schedule, precisely because the equipment is arriving. The gigawatt that has been talked about so much, which was such an ambitious statement, will be implemented with a conditional delay, which is absolutely understandable, due to the preparation of projects. At the same time, we have a lot of issued capacities for private business 

- Boyko said.

Recall

President of Ukraine Volodymyr Zelenskyy statedthat Ukraine has a clear plan to build up to 1 GW of gas-fired generation capacity this year.

Deputy Energy Minister Mykola Kolisnyk statedthat the construction of up to 1 GW of gas-fired generation capacity this year is realistic.

Popular
News by theme
Russian airstrike in Zaporizhzhia: three small children among the wounded

 • 16490 переглядiв

Consequences of Russian air strikes on Zaporizhzhia: the number of victims is growing

 • 16359 переглядiв

Deforestation in the Brazilian Amazon fell to a nine-year low

 • 14266 переглядiв

Cuba was left without electricity again amid hurricane

 • 14958 переглядiв

Russia's attack on Zaporizhzhia: one person killed, one year old child among the wounded

 • 15589 переглядiв